Kahramaa Phase 12 (3 No. 400kV Substation, 13 no. 132/11kV Substation)

GTC-643/H-153/2016

Kahramaa Phase 12 (3 No. 400kV Substation, 13 no. 132/11kV Substation)

Main Contractor:

Siemens W.L.L.- Qatar

Completion Year:

2017

Status:

Completed

Detail / Work Description:

For 11kV Cables
  • Supplying and installation of support structure.
  • Laying of 11kV cables.
  • Termination of 11kV cables.
  • Testing of 11kV cables.
  • Supplying and Installation of Sunshield Cable Protection for HV Cables 100, 132, 66kV

Substations:

# Substation Name Completion Year
1 400/132/11kV Al Sakhamah Substation 2017
2 400/132/11kV Bul Hemmaid Substation 2017
3 132/11kV Logistics Zone Super Substation 2017
4 220kV Ras Laffan 3 Substation 2017
5 400/220/132kV Doha South Super Substation 2017
6 132/11kV Wakrah Replacement Substation 2017
7 132/11kV Al Jahaniyah 3 Substation 2017
8 132/11kV Jeryan Jenaihat-1 Substation 2017
9 66/11kV Wakrah South Substation 2017
10 66/11kV Doha Industrial A Substation 2017
11 66/11kV Khalifat 2 Substation 2017
12 66/11kV Umm Shahrain Substation 2017
13 66/11kV Qatar Cool Substation 2017
14 132/11kV Al Thumamah Central Substation 2017

QEMC - QATAR

Electro-Mechanical Co. W.L.L - Qatar (QEMC)
Building No. 14, 3rd Floor, C Ring Road, Zone 27, St 230
P.O. Box: 31418, Doha-Qatar

(+974) 4436-4062    Fax : (+974) 4441-9596

qemc@emc.com.qa

emc.com.qa

JORDAN Office

Electro-Mechanical & Communication Engineers (EMC)
P.O. Box: 2693, 276 Prince Moh'd street - AMMAN - JORDAN

+ 962 6 4641960    Fax : + 962 6 4649960

emc@emc.com.jo

emc.com.jo

Follow us

Contact us and we'll get back to you within 24 hours.