Kahramaa Phase 7 Transmission Dept. (17 No of 220, 132 and 66 KV Substations)
KAHRAMAA GTC/123/2006
Kahramaa Phase 7 Transmission Dept. (17 No of 220, 132 and 66 KV Substations)
Main Contractor:
Siemens W.L.L.
Completion Year:
2009
Status:
Completed
Detail / Work Description:
Substations:
# | Substation Name | Completion Year |
---|---|---|
1 | MIC-3 (66/11kV) Substation | 2009 |
2 | MIC-2 (66/11kV) Substation | 2009 |
3 | NBK2 (66/11kV) Substation | 2009 |
4 | QRE (66/11kV) Substation | 2009 |
5 | Al-Dhahiya West (66/11kV) Substation | 2009 |
6 | Al-Dhahiya (132/66/11kV) Substation | 2009 |
7 | Wakrah-2 (132/66/11kV) Substation | 2009 |
8 | Muraikh North (66/11kV) Substation | 2009 |
9 | NDQ (66/11kV) Substation | 2009 |
10 | Mosemeer (66/11kV) Substation | 2009 |
11 | Abuhamour Central (66/11kV) Substation | 2009 |
12 | Al Sudan (66/11kV) Substation | 2009 |
13 | Khore Junction (66/11kV) Substation | 2009 |
14 | Ainhamad Substation Modification | 2009 |
15 | Ain Khalid South (66/11kV) Substation | 2009 |
16 | Al Wadi (66/11kV) Substation | 2009 |